Docket No: 13-035-196

RMP Application to Revise Electric Service Schedule 31

Docet Index

Docket Number: 13-035-196

In the Matter of: the Application of Rocky Mountain Power for Approval of Revisions to Back-Up, Maintenance, and Supplementary Power Service Tariff, Electric Service Schedule 31

249095

For questions regarding documents not linked call 801-530-6714

Date Description
September 29, 2014 Tariff Approval Letter from Commission
September 11, 2014 Comments from DPU
August 12, 2014 Action Request Due: September 11, 2014
August 12, 2014 Cover Letter
Electric Service Schedules Index (REV)

Electric Service Schedules Index (LEG)

* Exhibit A – First Revision of Sheet No. 31.1 (REV)

* Exhibit B – First Revision of Sheet No. 31.1 (LEG)

* Exhibit C – First Revision of Sheet No. 31.2 (REV)

* Exhibit D – First Revision of Sheet No. 31.2 (LEG)

* Exhibit E – First Revision of Sheet No. 31.3 (REV)

* Exhibit F – First Revision of Sheet No. 31.3 (LEG)

* Exhibit G – First Revision of Sheet No. 31.4 (REV)

* Exhibit H – First Revision of Sheet No. 31.4 (LEG)

* Exhibit I – First Revision of Sheet No. 31.5 (REV)

* Exhibit J – First Revision of Sheet No. 31.5 (LEG)

* Exhibit K – First Revision of Sheet No. 31.6 (REV)

* Exhibit L – First Revision of Sheet No. 31.6 (LEG)

* Exhibit M – First Revision of Sheet No. 31.7 (REV)

* Exhibit N – First Revision of Sheet No. 31.7 (LEG)

* Exhibit O – First Revision of Sheet No. 31.8 (REV)

* Exhibit P – First Revision of Sheet No. 31.8 (LEG)

August 6, 2014 Reporter’s Transcript Re: July 29, 2014
July 28, 2014 Email Comments from John Sohl
July 23, 2014 Order Confirming Bench Ruling
July 11, 2014 Fourth Order Modifying Scheduling Order and Notice of Hearings
July 10, 2014 Reporter’s Transcript Re: June 30, 2014
June 30, 2014 Certificate of Service to UIEC Stipulation
jUNE 30, 2014 Audio File for Stipulation Hearing held June 30, 2014
Part 1
Part 2
June 25, 2014 Cover Letter
RMP Settlement Stipulation
* Exhibit A – Schedule 31 Tariff Sheets
June 24, 2014 Corrected Petition for Leave to Intervene of Southwest Energy Efficiency Project
June 23, 2014 Third Order Modifying Scheduling Order and Notice of Hearings
June 23, 2014 DPU Motion to Amend Schedule and Request for Stipulation Hearing
June 19, 2014 Second Order Modifying Scheduling Order
June 16, 2014 First Order Modifying Scheduling Order
June 4, 2014 Order Granting Intervention of Southwest Energy Efficiency Project
May 22, 2014 Direct Testimony and Exhibit of Maurice Brubaker on behalf of UIEC
* Exhibit A – UIEC Exhibit COS 2.1 (MEB-1) – PacifiCorp Monthly Load Shape
* Exhibit B – UIEC Exhibit COS 2.2 (MEB-2) – Utah Jurisdiction Monthly Load Shape
* Exhibit C – UIEC Exhibit COS 2.3 (MEB-3) – RMP
* Exhibit D – UIEC Exhibit COS 2.3 (MEB-3) – RMP
* Exhibit E – UIEC Exhibit COS 2.3 (MEB-3) – RMP
* Exhibit F – UIEC Exhibit COS 2.6 (MEB-6), Summary
* Exhibit G – UIEC Exhibit COS 2.6 (MEB-6), Schedules 1-2 and 4-13 (1)
* Exhibit H – UIEC Exhibit COS 2.7 (MEB-7) – Regular Utility Service
* Exhibit I – UIEC Exhibit COS 2.8 (MEB-8) – RMP Partial Requirements Service Proposal
* Exhibit J – UIEC Exhibit COS 2.9 (MEB-9) – RMP Electric Service Schedule No 31
* Exhibit K – UIEC Exhibit COS 2.10 (MEB-10) – Standby Rates for Combined Heat and Power Systems
Certificate of Service
May 22, 2014 Redacted Direct Testimony of Jonathan A. Lesser on behalf of UIEC
* Exhibit A – UIEC COS 1.1 – Classification and Allocation of Generation Fixed Costs
* Exhibit B – UIEC COS 1.2 – PacifiCorp 2013 Stress Factor Analysis
* Exhibit C – UIEC COS 1.3 – RMP Stress Factor Study Proposal
* Exhibit D – UIEC COS 1.4 – Rates as of June 1, 2013
* Exhibit E – UIEC COS 1.5 – Schedule 75 Partial Requirements Service
* Exhibit F – UIEC COS 1.6 – Puget Sound Energy
Certificate of Service
Direct Testimony of Jonathan A. Lesser on behalf of UIEC [PROPRIETARY]
May 22, 2014 Prefiled Direct Testimony of Artie Powell PhD for DPU
Certificate of Service
May 22, 2014 Direct Testimony of Roger Swenson for US Magnesium, LLC
May 22, 2014 Appendix A – Christine Brinker
May 22, 2014 Cover Letter
Direct Testimony of Christine Brinker on Behalf of SWEEP
* Exhibit A – SWEEP Exhibit 1.1 Statement of Qualifications for Christine Brinker
* Exhibit B – SWEEP Exhibit 1.2 Standby Rates for Combined Heat and Power Systems
Certificate of Service
May 15, 2014 Petition for Leave to Intervene of Southwest Energy Efficiency Project (SWEEP)
April 7, 2014 Appendix A Re: Mindy Peiffer
Certificate of Service
March 25, 2014 Appendix A Re: Roger Swenson
March 14, 2014 Order Granting Intervention of Wal-Mart Stores, Inc. and Sam’s West, Inc.
March 6, 2014 Appendix A Re: Jonathan Lesser, James R. Dauphinais, James Slecky, Brian C. Collins, Maurice Brubaker, Vicki M. Baldwin, and William J. Evans

Certificate of Service

February 20, 2014 Cover Letter
Petition to Intervene of Walmart Stores, INc. & Sam’s West Inc.
February 20, 2014 Order Granting Intervention of US Magnesium LLC
February 20, 2014 Order Granting Intervention of Utah Association of Energy Users
February 12, 2014 Order Granting Intervention of Kennecott Utah Copper LLC and Tesoro Refining and Marketing Co.
February 10, 2014 Email Correspondence from Stanley T. Holmes
January 31, 2014 Appendix A Re: Gary A. Dodge
January 31, 2014 Petition to Intervene of US Magnesium LLC
January 31, 2014 Petition to Intervene of UAE
January 24, 2014 Email Correspondence from Bill Hanewinkel
January 23, 2014
UIEC Petition to Intervene
January 22, 2014 Scheduling Order, Notice of Scheduling Order Suspension and Notice of Hearings
December 12, 2013 Scheduling Order and Notice of Hearing
December 5, 2013 Notice of Scheduling Conference
December 4, 2013 Action Request Due 1-3-2014
December 4, 2013 Cover Letter
RMP Application to Revise Electric Service Schedule 31
* Exhibit A – Direct Testimony of Joelle R. Steward
* Exhibit B – Electric Service Schedule No. 31
* Exhibit C – Electric Service Schedule No. 31 – Cont.
* Exhibit D – Electric Service Schedule No. 31 – Cont.
* Exhibit E – Electric Service Schedule No. 31 – Cont.
* Exhibit F – Electric Service Schedule No. 31 – Cont.
* Exhibit G – Electric Service Schedule No. 31 – Cont.
* Exhibit H – Electric Service Schedule No. 31 – Cont.
* Exhibit I – Electric Service Schedule No. 31 – Cont.
* Exhibit J – Partial Requirements Service Proposal
* Exhibit K – Partial Requirements Service Proposal Full Sheet

Share this: