Date |
Description |
January 23, 2004 |
Petition
* Exhibit A – Power Purchase Agreement
* Exhibit B – Prefiled Direct Testimony of Roger J. Swenson |
January 26, 2004 |
Action Request, Due: March 26, 2004 |
March 15, 2004 |
Motion for Protective Order |
March 19, 2004 |
Notice of Scheduling Conference |
March 22, 2004 |
Protective Order |
March 23, 2004 |
Appendix A, Re: Kelly Francone |
March 24, 2004 |
Scheduling Order |
March 24, 2004 |
Appendix A, Re: Daniel Gimble |
April 1, 2004 |
Contract Issues |
April 14, 2004 |
Correspondence from Patricia E. Schmid |
April 19, 2004 |
Prefiled Supplemental Direct Testimony of Roger Swenson |
April 20, 2004 |
Exhibit A, Re: Philip Hayet |
June 4, 2004 |
Second Scheduling Order |
June 4, 2004 |
Petition to Intervene of US Magnesium LLC |
June 18, 2004 |
Amended Notice of Hearing |
June 19, 2004 |
Email from Commission |
July 12, 2004 |
Order Granting Intervention granted to US Mag |
July 21, 2004 |
Fourth Scheduling Order |
July 28, 2004 |
Amended Notice of Hearing |
July 28, 2004 |
Order Granting Intervention granted to US Mag |
July 29, 2004 |
Reporter’s Transcript of Hearing |
August 5, 2004 |
Amended Power Purchase Agreement
* Exhibit A – Description of Sellers Facility |
September 1, 2004 |
Letter from Julie Orchard |
September 22, 2004 |
Comments from PacifiCorp |
September 23, 2004 |
Desert Power’s Late-Filed Exhibits 1-4
* Exhibit A Letter to Commissioners -Response to request for additional comments
* Exhibit B – O&M Discussion Points
* Exhibit C – DP Late-Filed Exhibit 3
* Exhibit D – DP Late-Filed Exhibit 4 |
October 7, 2004 |
Order Approving Desert Power’s Qualifying Facility Contract |
February 10, 2006 |
Notice of Force Majeure |
April 4, 2006 |
Correspondence between Stephen F. Mecham and PacifiCorp |
May 9, 2006 |
Correspondence between PacifiCorp and Stephen F. Mecham |
May 19, 2006 |
Response of Desert Power |
August 9, 2006 |
Emergency Petition for Resolution of Dispute Pursuant to Section 21 of Power Purchase Agreement and Proposed Schedule
* Exhibit A – Letter 7/14/06
* Exhibit B – Letter 7/19/06
* Exhibit C – Letter 8/4/06
* Exhibit D
*Exhibit D1 [PROPRIETARY]
* Exhibit E – Letter 8/7/06
* Exhibit F – Letter 8/7/06 |
August 10, 2006 |
Rocky Mountain Power’s Opposition to Proposed Schedule for Emergency Petition |
August 11, 2006 |
Notice of Scheduling Conference |
August 16, 2006 |
Scheduling Order |
August 18, 2006 |
Prefiled Direct Testimony of Roger J. Swenson on Behalf of Desert Power, L.P.
* Exhibit A
* Exhibit B
* Exhibit C
* Exhibit D
* Exhibit E
* Exhibit F
* Exhibit G
* Exhibit H |
August 18, 2006 |
Prefiled Direct Testimony of Charles Darling for Desert Power, L.P.
* Exhibit A* Exhibit B [PROPRIETARY] |
August 25, 2006 |
Rebuttal Testimony of Douglas N. Bennion |
August 25, 2006 |
Rebuttal Testimony of Kenneth T. Houston |
August 25, 2006 |
Rebuttal Testimony of Bruce W. Griswold
* Exhibit A
* Exhibit B
* Exhibit C |
August 28, 2006 |
Late-Filed Exhibit for the Testimony of Charles Darling Filed 08/18/06 |
September 6, 2006 |
Correspondence from Tooele County |
September 6, 2006 |
Reporter’s Transcript, 08/31/06 Technical Conference |
September 6, 2006 |
Direct Testimony of Andrea Coon
* Exhibit A – Certificate of Service
* Exhibit B – Time line of contact between Desert Power and PacifiCorp Transmission
* Exhibit C |
September 7, 2006 |
Comments from the Committee of Consumer Services |
September 7, 2006 |
Motion to Compel Discovery |
September 7, 2006 |
Correspondence from Representative Jim Gowans |
September 12, 2006 |
Correspondence from Stephen F. Mecham |
September 19, 2006 |
Notice of Withdrawal of Motion to Compel Discovery
* Confidential Version |
September 19, 2006 |
Email from Steve Mecham |
September 20, 2006 |
Report and Order Resolving Desert Power Contract Dispute |
September 20, 2006 |
Cover Letter
MMC Energy, Inc. Form 8-K Report |
September 25, 2006 |
Emergency Petition for Expedited Clarification of Report and Order Resolving Desert Power Dispute Issued September 20, 2006
* Exhibit A – Correspondence from PacifiCorp to Stephen F. Mecham |
September 26, 2006 |
Response to Emergency Petition for Expedited Clarification |
September 26, 2006 |
Limited Reply of the Division of Public Utilities to Desert Power’s Emergency Petition for Expedited Clarification of Report and Order Resolving Desert Power Dispute Issued September 20, 2006 |
October 2, 2006 |
Order on Request for Clarification |
October 5, 2006 |
Reporter’s Transcript of 9-8-06 |
October 20, 2006 |
Request for Expedited Reconsideration, Review, or Rehearing |
October 23, 2006 |
Response to Request for Expedited Treatment of Petition for Reconsideration, Review, or Rehearing |
October 25, 2006 |
Notice of Desert Power’s Filing for Bankruptcy Protection |
November 8, 2006 |
Order on Second Request for Reconsideration or Rehearing, Amending October 2, 2006, Clarification Order |
December 26, 2006 |
Petition for Explanatory Statement of Prior Order and Petition for Hearing |
December 29, 2006 |
Notice of Hearing |
January 8, 2007 |
Position Statement of Rocky Mountain Power |
January 8, 2007 |
Position Statement of Desert Power on the effect of commission order in this docket dated September 20, 2006, October 2, 2006 and November 8, 2006 |
January 11, 2007 |
Position Statement of the Utah Division of Public Utilities in Response to Desert Power’s Emergency Petition for Expedited Clarification of Report and Order Resolving Desert Power Dispute Issued September 20, 2006 |
January 16, 2007 |
Ruling on Request for Explanatory Statement |
February 5, 2007 |
Pacificorp’s Statement of Non-Opposition to Debtors’ Motion to Assume Pacificorps Power Purchase Agreement |
February 23, 2007 |
Bankruptcy Form B10 |
March 12, 2007 |
Stipulation to Extend Time |
Share this: