Docket No: 06-999-03

PURPA Standards

Docket Index

Docket Number: 06-999-03

In the Matter of: Consideration of the Amendment of 16 U.S.C. Section 2621 – Consideration and Determination Respecting Certain Ratemaking Standards for Electric Utilities by the Energy Policy Act of 2005

For questions regarding documents not linked call 801-530-6714

Utah’s Clean Energy Comments

Date Description
October 26, 2016 Order
September 13, 2016 Reply Comments from Rocky Mountain Power
August 29, 2016 Comments from the Division of Public Utilities
June 30, 2016 Notice of Comment Period
August 24, 2011 Technical Conference – Fossil Fuel
May 2, 2011 Cover Letter Re:11-999-01
Exhibit A – Fossil Fuel Energy Efficiency Standard Plan
Exhibit B – Carbon Plant Heat Rate Improvement Plan
November 30, 2010 Order Modifying Filing Schedule for Rocky Mountain Power’s Fossil Fuel Generation Efficiency Annual Plan
May 3, 2010
Re: 10-999-01
Cover Letter
Rocky Mountain Power’s Fossil Fuel Energy Efficiency Standard Plan Exhibit A – Carbon Plant Heat Rate Improvement Plan
Exhibit B – Dave Johnston Plant Heat Rate Improvement Plan
Exhibit C – Huntington Plant Heat Rate Improvement Plan
Exhibit D – Hunter Plant Heat Rate Improvement Plan
Exhibit E – Jim Bridger Plant Heat Rate Improvement Plan
Exhibit F – Naughton Plant Heat Rate Improvement Plan
Exhibit G – Pacificorp Energy Heat Rate Improvement Plan
Exhibit H – Wyodak Plant Heat Rate Improvement Plan
May 28, 2009 Notice of Technical Conference
March 31, 2009 Rocky Mountain Power’s Fossil Fuel Energy Efficiency Standard Plan
Exhibit A
Exhibit B
Exhibit C
Exhibit D
Exhibit E
Exhibit F
Exhibit G
Exhibit I
July 21, 2008 Correspondence from Julie Orchard
May 21, 2008 Rocky Mountain Power Fossil Fuel Energy Efficiency Standard Plan
Exhibit A
December 4, 2007 Notice of Technical Conference
August 20, 2007 Notice of Technical Conference
August 10, 2007 Determination Concerning the PURPA Fossil Fuel Generation Efficiency Standard
July 6, 2007 Comments from the Committee of Consumer Services
July 2, 2007 Rocky Mountain Power Decision Summary Report on PURPA Time-Based Metering and Communication Standard
June 26, 2007 Rocky Mountain Power Comments on the Division of Public Utilities’ Recommendations Concerning Fossil Fuel Energy Efficiency Standard
May 29, 2007 Request for Comments
May 23, 2007 Revised Comments from DPU – Fossil Fuel Generation Efficiency Standard
May 18, 2007 Comments from DPU
May 8, 2007 Determination Concerning the PURPA Net Metering and Interconnection Standards
April 4, 2007 Net Metering Letter
April 2, 2007 Comments from Mt. Wheeler Power
April 2, 2007 Public Comment from Jim French
March 28, 2007 Interconnection Standard Comments from Utah Clean Energy and Intermountain CHP Application
March 28, 2007 Net Metering Comments from Utah Clean Energy and Intermountain CHP Application
March 28, 2007 Utah Rural Electric Association Comments
March 28, 2007 CCS Comments Re: Net Metering Standards
March 28, 2007 Committee of Consumer Services Comments
March 28, 2007 UIEC Comments
March 28, 2007 RMP Comment Concerning Interconnection Standard
March 20, 2007 Comments from the Clean Air Coalition
March 13, 2007 Determination Concerning the PURPA Fuel Sources Standard
March 6, 2007 Request for Comments
March 2, 2007 Comments from DPU – Interconnection Recommendation
March 1, 2007 Comments from DPU – Net Metering Recommendation Memo PURPA
February 26, 2007 Rocky Mountain Power Comments
February 26, 2007 Net Metering Report
February 26, 2007 January 10, 2007 Technical Conference Minutes
February 23, 2007 Committee of Consumer Services Memo Re: Fuel Sources
February 14, 2007 Determination Concerning the PURPA Time-Based Metering and Communications Standard
February 6, 2007 Dixie Escalante Electric Comments
February 5, 2007 Request for Comments
February 5, 2007
February 1, 2007 Comments from Department of Public Utilities
January 29, 2007 Comments from the Moon Lake Electric
January 26, 2007 Comments from the Utah Rural Electric Association
January 25, 2007 Comments from Rocky Mountain Power
January 24, 2007 Comments and Recommendations of the Utah Association of Energy Users on PURPA Time-Based Metering and Communications Standard
January 24, 2007 Comments from the Utah Industrial Energy Consumers
January 24, 2007 Comments from the Committee of Consumer Services
January 9, 2007 Request for Comments
January 8, 2007 Comments from DPU
Exhibit A
January 5, 2007 Technical Conference Minutes 12-18-06
December 4, 2006 Cellnet Technology, Inc. and Hunt Technologies, LLC Comments to the DPU Working Document regarding Time-based metering and communications standard in the Matter of the Investigation of the Amendments to PURPA by the 2005 Energy Policy Act
November 22, 2006 Technical Conference 11-09-06; Smart Metering
November 17, 2006 Notice of Technical Conferences
October 31, 2006 Amended Notice of Technical Conference
October 31, 2006 Entry of Appearance and Motion for Full Party Status for Hunt Technologies, Inc.
October 30, 2006 Notice of Technical Conference
October 24, 2006 Technical Conference 10-17-06: Fuel Sources, Fossil Fuel Generation Efficiency
October 12, 2006 PURPA Work Group Meeting Minutes 10-06-06
October 10, 2006 Notice of Technical Conference
Ocotober 5, 2006 PURPA Work Group Meeting Minutes 9-19-06
September 5, 2006 Technical Conference Minutes 08-30-06
September 5, 2006 Names and Numbers of Interested Parties
August 30, 2006 Technical Conference Follow-up Documents:
1) 08/30/2006 Technical Conference Power Point Presentation
2) 08/30/2006 Technical List of Attendees
3) Distributed Energy (CHP) Report
a. Appendix A to Distributed Energy Report
b. Appendix B to Distributed Energy Report
4) PacifiCorp Time-of-Use Report
5) FERC Demand Response and Smart Metering Report
July 20, 2006 Notice of Technical Conference
July 17, 2006 Correspondence from Julie Orchard
July 17, 2006 Background documents summarizing the requirements of this docket:
Background information
Requirements
July 14, 2006 Notice of Scheduling Conference

Share this: